Project with Completed By
Factory building – Apr 2023
DG panel room – May 2023
Fabrication yard – May 2023
Scrap yard – May 2023
Bike & Car parking – May 2023
Size
1600 MT
Duration
6 Months
Location
Pochampalli
About Project
A 1600 MT factory development in Pochampalli, executed in 6 months. The project included the main factory building, DG panel room, fabrication yard, scrap yard, and parking facilities. Scope covered 3D modeling, drawing detailing, fabrication, and erection for timely and precise delivery.
Scope of Work
Our scope of work covers end-to-end solutions to bring your project to life with precision and efficiency:
3D Modeling
Drawing Detailing
Fabrication
Erection